During the PR to PO conversion (ME59N), how to check availability of material in stock.

Oct 26, 2017 at 06:14 PM

41

avatar image
Former Member

During the PR to PO conversion (ME59N), check availability of material in stock and if insufficient quantity present then don't create PO for that line item. For this i have implemented exit EXIT_SAPLME59_001 and updated PR ( clear fixed vendor and supply plant ) to stop creation of PO. Although the PR is getting updated but the PO still gets created despite no material in stock.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Dibyendu Patra Oct 28, 2017 at 01:59 PM
0

May be it is not enough to remove the fixed vendor and plant. Try to remove all information for source supply tab e.g. info record, agreement.