Skip to Content
0
Former Member
Dec 27, 2007 at 01:39 PM

Planning board setting

328 Views

Hi Friends,

I'm trying to see progress figures on barchart in planning board. I made following settings in planning board.

Settings - Option - Data bar text - text type - variable description. I selected Duration, Decription, past, Delay, & Agg Plan POC in given five cells

The observation is, all data except 'POC' appeared as required. I interchanged the field locations & also tried other POC related elements. but did not work.

I was informed that cnse5 & cj2b are two different programms & progress data will not be seen on barchart as required. now I have no option but to see cn48 or cnse5 report if I want to see uptodate confirmation or put further confirmation on activity.

Is that correct way?

Will experts give their opinion?

Regards,

Mohan Parab