Hi all,
We are doing Physical Inventory with Cycle Counting...
Now issue is that in MICN (Cycle Counting), Materials are selected Batchwise, So if two batches are there of a single material then both the batches should be for cycle counting....
E.G. Material : A
Batch : B1 --> 1st January
Batch : B2 --> 10th January
Cycle Count Date --> 20th January
So both batches would be eligible for cycle counting....
But if another batch is created on 21st of January...It would not be considered for cycle count on next run because its date of creation is different and that batch would be eligible for cycle count on 21st of next month....
Now we want to calculate all the batches of a single material on a particular date....Is there any solution for it?