cancel
Showing results for 
Search instead for 
Did you mean: 

Clarification regarding plan activty price and actual activity price

Former Member
0 Kudos

Hello Experts,

Need your help on the below issues...

I have maintained the manual plan price for activities in kp26 but if I maintain the actual price manually in KBK6 then will I be able to run the revaluation of order using "MFN1"? If not then how do I run the revaluation.

2-> what if I maintain the manual plan price for activities in kp26 then how do I calculate the actual activity price.

Accepted Solutions (1)

Accepted Solutions (1)

former_member513101
Active Contributor
0 Kudos

Hi Rahul,

Not recommend you direct maintain the actual price to KBK6. You should run KSS2 and KSII to get the actual price. System will save the actual price to KBK6 when you save the price in KSII. MFN1 and CON2 are to post the activity price variance between KP26 and KBK6 to production order and production cost center. After you run MFN1 or CON2, you will get zero over/under absorption production cost center in report S_ALR_87013611.

Thanks.

Former Member
0 Kudos

Hi KK Lam,

I appreciate your response. but the thing is that we are not using cost center split. If I maintain the Manual price in kp26 then How will get the actual price. Could you please help me with the steps to achieve this.

I would be really thankful to you if you help me in this regard.

Regards,

Rahul

former_member513101
Active Contributor
0 Kudos

HI Rahul,

KP26 is the planned activity rate. Your actual activity price is from your actual payroll, depreciation and so no. So, after you post the payroll, depreciation, and etc. Then you run KSII without KSS2 if cost center splitting is not required, system will calculate the actual activity price.

Thanks.

Former Member
0 Kudos

Hi KK Lam,

Thanks for helping me here. My only doubt is that if I maintain the plan price manually in kp26 then how will I capture the actual activity price calculation.

2->how will the revaluation at actual works: Production/Process order works

Regards,

Rahul

former_member513101
Active Contributor
0 Kudos

Hi Rahul,

As i mentioned, KP26 is planned activity rate. When you confirm the activity hours / unit for production / process order you get the actual hours / unit times the KP26 rate. Here you get the standard activity cost.

2. Your actual activity cost is from payroll, depreciation and etc from FI posting or from HCM interface to FI. with these actual cost and the actual hours / unit from production / process order confirmation. You will get the actual rate when you run KSII. Actual cost / actual quantity = actual activity rate.

Thanks.

former_member513101
Active Contributor
0 Kudos

Hi Rahul,

Read this as well.

https://archive.sap.com/discussions/thread/1185347

Thanks

Former Member
0 Kudos

Thanks KK Lam,

I appreciate your help..

former_member513101
Active Contributor
0 Kudos

Hi Rahul,

You are welcome. Hope i answer your question

Thanks

Former Member
0 Kudos

Yes KK Lam.. much appreciated..

larissaleon
Explorer
0 Kudos

Hi KK Lam,

Sorry to bether you, and enter into this question, but I am facing a similar problem and have some doubts. I opened this question for more detail (https://answers.sap.com/questions/406901/ksii-not-balancing-cost-center-actual-rate.html).

Basically what I wan to know is, as you are saying: "After you run MFN1 or CON2, you will get zero over/under absorption production cost center in report S_ALR_87013611." but in this company they are not runing MFN1 or CON2 and they are getting in other months "zero over/under absorption production cost center" but in the month I am runing the same procedure, I am not getting the Zero. Do you have any ideas?

thanks!!! 🙂

Larissa

Answers (2)

Answers (2)

former_member259539
Active Participant
0 Kudos

i just tested a scenario maintained manually price in KP26 and then i created a process order and issued material on it and then i did confirmation. i posted primary cost from FI to production cost center. After that i used KSII T-code for actual price calculation. then i used MFN1 Tcode for revaluation of production order. when i checked the S_ALR_87013611 - Plan/Actual Comparisons -> Cost Centers: Actual/Plan/Variance. All the variance from the cost center were posted to the production order

Former Member
0 Kudos
That is my answer..it means even if we maintain the rate manually in kp26 and do confirmation and post some primary cost from fi to production cost center. after that if we run KSII then we will reach actual activity price calculation & we will get the revaluation using MFN1.

Means revaluation will be done..

former_member259539
Active Participant
0 Kudos

yes but you must test it for yourself on DEV server. especially if splitting is not in used . i tested it on S4HANA1610.

former_member259539
Active Participant
0 Kudos

how you are calculating KP26 value? is it manually maintained then you are not able to calculate actual price which will results in variance at cost center level

if you are calculating it via KSPI then you can revaluate you production orders at month end.

Former Member
0 Kudos

Hello Muhammad,

yes, we are maintaining the value manually in kp26. but my question is that if the plan price is maintained manually in kp26 then how will I capture the actual activity price calculation.

2->how will the revaluation at actual works: Production/Process order works

Regards,

Rahul

former_member259539
Active Participant
0 Kudos

you cannot do it with manual price maintenance in kp26 because system doesnot even know about total planed or actual quantity against cost element

for KSPI calculation you first maintained planned activity in KP26 then use KP26 t-code for maintaining planned cost.cost center splitting is also used. without this process you cannot revaluate production orders