Skip to Content
avatar image
Former Member

Clarification regarding plan activty price and actual activity price

Hello Experts,

Need your help on the below issues...

I have maintained the manual plan price for activities in kp26 but if I maintain the actual price manually in KBK6 then will I be able to run the revaluation of order using "MFN1"? If not then how do I run the revaluation.

2-> what if I maintain the manual plan price for activities in kp26 then how do I calculate the actual activity price.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Oct 27, 2017 at 02:12 AM

    Hi Rahul,

    Not recommend you direct maintain the actual price to KBK6. You should run KSS2 and KSII to get the actual price. System will save the actual price to KBK6 when you save the price in KSII. MFN1 and CON2 are to post the activity price variance between KP26 and KBK6 to production order and production cost center. After you run MFN1 or CON2, you will get zero over/under absorption production cost center in report S_ALR_87013611.

    Thanks.

    Add comment
    10|10000 characters needed characters exceeded

    • Hi KK Lam,

      Sorry to bether you, and enter into this question, but I am facing a similar problem and have some doubts. I opened this question for more detail (https://answers.sap.com/questions/406901/ksii-not-balancing-cost-center-actual-rate.html).

      Basically what I wan to know is, as you are saying: "After you run MFN1 or CON2, you will get zero over/under absorption production cost center in report S_ALR_87013611." but in this company they are not runing MFN1 or CON2 and they are getting in other months "zero over/under absorption production cost center" but in the month I am runing the same procedure, I am not getting the Zero. Do you have any ideas?

      thanks!!! :)

      Larissa

  • Oct 27, 2017 at 10:14 AM

    how you are calculating KP26 value? is it manually maintained then you are not able to calculate actual price which will results in variance at cost center level

    if you are calculating it via KSPI then you can revaluate you production orders at month end.

    Add comment
    10|10000 characters needed characters exceeded

    • you cannot do it with manual price maintenance in kp26 because system doesnot even know about total planed or actual quantity against cost element

      for KSPI calculation you first maintained planned activity in KP26 then use KP26 t-code for maintaining planned cost.cost center splitting is also used. without this process you cannot revaluate production orders

  • Oct 28, 2017 at 03:38 PM

    i just tested a scenario maintained manually price in KP26 and then i created a process order and issued material on it and then i did confirmation. i posted primary cost from FI to production cost center. After that i used KSII T-code for actual price calculation. then i used MFN1 Tcode for revaluation of production order. when i checked the S_ALR_87013611 - Plan/Actual Comparisons -> Cost Centers: Actual/Plan/Variance. All the variance from the cost center were posted to the production order

    Add comment
    10|10000 characters needed characters exceeded