'Dear Sirs,

I have an issue regarding goods issue during production confirmation.

Scenario is like this, I have a BOM component whose unit of measure is in "EA" . For base quantity of 10 for the parent material (A) 1 "EA" component (B) is required. When we produce more than 50% of material "A" system proposes correctly during production confirmation goods movement, but when we produce less than 50% system doesn't propose component material quantity.

My requirement is that, system should propose component quantity as 1 even if the produced quantity is less than 50%.

Thanks in advance,