What is the purpose of With qty structure check box in Material Master in costing view 1.

To my understanding it is only to improve the performance of system. hence the reason the check can even be maintained for raw materials having price control V in accounting view 1, External procurement in procurement type in MRP2.

Please explain your views.

Regards

KM Naidu

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 26, 2007 at 07:18 PM

    Costing in sync with a BOM and routing is implied onto a quantity structure.An actual quantity structure is created from goods movements and the associated flows of actual quantities, and is based on procurement alternatives and procurement processes.

    Basically , It is used for multilevel material price determination in actual costing.

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 26, 2007 at 09:25 PM

    If this indicator is set, the material is costed using costing with a quantity structure (BOM and routing).

    The system searches for any existing cost estimates with quantity structure for the individual materials; it ignores existing cost estimates without quantity structure. If the system does not find any valid costing data for the materials, it costs the material or accesses the price in the material master.

    If this indicator is not set, the planned costs for the material are calculated using the cost estimate without quantity structure. In this case, you use unit costing to create the quantity structure manually by entering costing items for materials and activity types, for example.

    The system now searches for any existing cost estimates without quantity structure. If a cost estimate without quantity structure exists for a material, the results of this cost estimate are included in a cost estimate with quantity structure. If there is no cost estimate without quantity structure, the cost estimate with quantity structure accesses the price in the material master record. The planned costs for this material then go into the cost estimate with quantity structure as raw material costs.

    This does not apply if the indicator Ignore prod cost est w/o qty structure is set in the costing variant.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.