How to transport a Report (Report Painter) from QAS to PRD!!!!!!!!!!

Former Member
0 Kudos

I have created a new 'Z' Report in QAS and i need to transport it to PRD, but don't know how!.

I already went by SPRO! Controlling - Profitabilitty Analysis - Information System - Report Components - Define Froms - Define forms for Profitabillity Reports then change form.

Then use the transport icon. SE09 Released the order and now what???? STMS? Already tryed it in QAS and PRD and nothing.

Please help. Thx in advance

Regards to all

Rui Ribeiro

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rui,

Thats a basis job to do?

After releasing..

You need to go to STMS ..

In Import queue you will see all the list..

select the request number and then click on the truck button..

If you havent imported a request before i would suggest you better take ask someone else to do it for you.

Regards,