No changes history in MM after cost roll PP2 for assembly material

Cost roll planned price 2 for assembly by using CK11N and update using CK24.

After done, the correct PP2 price is updated on the MM PP2 field of FERT and HALB material. But we can't see any history done from Environment >> Display changes view.

Any tcode/ report we can pull to see the history(old and new value, done by, date done) done on MM PP2 field?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 28, 2017 at 07:24 AM

    Look into the KBA document 2424112 - Change document missing in MM04 from CK40n/CK24, also check 2012338 - Change document cannot be found in transaction MM04 when material is changed.