Hello Experts,

We are facing an issue in production regarding the process chain.

One of the variant in process chain gets stuck in yellow, stopping the next variants to run hence making the PC status yellow forever.

When i have checked in RSPCPROCESSLOG, State = G and Actual state = J (ramework error upon completion). Hence executing the program RSPC PROCESS FINISH has also not worked.

I suspect that this is because the chain starts as a meta chain (1st run) and as a sub chain of another PC(2nd run) at the same time.

When we repeat the red request in 2nd run, it gets completed successfully and we can see the status of 1st run as below in ST13

capture1.png

Please help me in resolving the issue.

This PC is event based.

Thanks,

Sahana

capture.png (4.4 kB)
capture1.png (1.8 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Shanthi Bhaskar Oct 30, 2017 at 05:15 PM
0

try to change the RSPCPROCESSLOG Actual state to G in debug mode, I know changing the SAP table entries were not recomended, first check with your basis/manager before doing this.

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Nov 02, 2017 at 12:31 PM
0

Hello Shanthi,

RSPCPROCESSLOG actual state is already G.

Thanks,

Sahana