Dear Gurus,
We are automotive manufacturing unit using REM. Earlier we were not using planning run. Now we have started planning using MDBT. In order to restrict the material selection we have used User Exit on Storage location. Error which we encounter is "Error determining planning periods for the calender".
Material Master relevant fileds are:
MRP type: PD
Lot Size: TB (daily lot size).
Indi/ Coll: 2
Planning Calander: none
But when we use standard User Exit on MRP controller the system does not post any error msg of planning periods.
Pls guide.
Regards,
Pradeep Santara