HI,

Greetings!!!!

In Budget return process, we can return the budget if it is not released. But if budget released we can't return it, for that we are reducing the budget equal to Assigned budget and completing the returns process. But by mistake enter the value less than the Assigned budget and click on the Check Option, system not throwing any error message why?.

Please let us know how we can control this.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
avatar image
Former Member Oct 27, 2017 at 11:42 AM
0


Hi,

you need to put error for activity 06(Budgeting) in defining tolerance limits for your budget profile

Regards

Kalpesh Agrawal

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi,

Thank you very much for your support. After assigning the Transaction Group 06 in Budget Tolerance limits issue resolved.

Regards

J.K