on 12-25-2007 10:54 AM
Dear All
In planned order change mode we have a option for Component Overview and Explode BOM.Is there any difference in this option.
We are not finding any details about Operation Overview.
I would like to know your comments on this.
Regards
Shankar
Hi Shankar,
U cannot see the operation overview like in Production order.
But if u do the manual sheduling u can see the operation scheduling results under detailed scheduling tab.
Please comeback for moer diubts.
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shankar,
There is no difference between them.
You cannot c operation untill u convert it into PO.
Either you can c through production version assign in it
Regards,
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi shankar,
Do u mean to say u donot get any component list in Both component over view and Bill of material option screen
i donot see any difference.
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.