Hi SAP gurus,

In sales order, we carry out availability check. Suppose the ATP quantity is X. But after its delivery, the ATP quantity is not decreasing at the time of next check.

can You tell me what would be the reason and possible solutions?

-Prashant

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Check in OVZ9 or SD-BF-Availability check-Availability check against ATP-Carry out control for AC.

Check Include deliveries check box for the corresponding availability check and checking rule options.

Reward if helpfullllll............

Former Member
0 Kudos

check avaliabailty check settings and aganist ur requiremnt type select material block for others. try this i am not sure, if it works ok

Former Member
0 Kudos

please check ur TOR settings at delivery level. check at OVZ9, check u req. type must pass order/delivery requirements.

reward if it is useful

Lakshmipathi
Active Contributor
0 Kudos

Dear Prashant

What checking rule you are following to the said plant?? Normally ATP check is controlled in OVZ9 where you define what requirements should be included while you run ATP check.

Thanks