Skip to Content

bydesign analytics Create Key Figure compare with Today

in ByDesign, We want to have the difference between Today and Planned Finish Date on the report, to help us understand the progress for each project or task by days.

I have gone thru all the fields and failed to figure out a way to realize this. Do you have any experience with this?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 02, 2017 at 03:31 AM

    Hi,

    If you are building this datasource in SDK you can use Transformation, it is a third wizard screen, select your date calculate Duration with other date.

    With an another approch you can check my this blog

    https://blogs.sap.com/2016/04/22/use-date-data-type-field-as-key-figure-in-analytics/

    Regards

    Sunil

    Add comment
    10|10000 characters needed characters exceeded