Hi
How to create a change number for a material?
Please Provide a step by step guidance, Is it possible send me a screen shot to create a change number.
Using the Change number, How can I create a revision level in BOM for that Material.
Thanks in Advance
Dear Madhan Shan,
Assuming that you have done the SPRO settings for ECM,I'm
giving you the details.
Creating a change number for a material:
1.Without Release key ,Change Note Creation(Whichs used
for material creation& change)---- T.Code CC01----->The Type
must be Change Master----->Function must be Without
Release key.Press Enter.
2.Give the Description whatever you want
Give the Valid from date as systems date(on which date you
are creating),As per your SPRO settings it will allow you to
mention the date.And give the change no status as 1 and
press enter.
3.Include the tick mark agianst material,document,Task list.
If the tick mark is not included means this change number
cant be used for that particular object,
For Eg here we havnt included for characteristic,so this cant
be used for creating or changing characteristics.
4.Save the data and the system gives you a message Change
number *** created.
5.Use this number while creating & changinthe material
master.
Creating Change Number for BOM:
1.Use same T code CC01 for creating a change
number,select the radio button for with Release key or without
release key.
2.Enter the details as said for material.
3.Include the tick for the check boxes against BOM in Object
types.
4.Use thisnumber for BOM creation & change.
Notes:
1.Same ECN can be used for material & BOM,if the tick mark
is included for the check boxes against material,BOM in
Object Types in CC01 T code.
2.With Release key Change number is used for Rotuing &
BOM.
3.If you use with release key change number for BOM,after
creating the BOM,release the change number key in CC02 t
code.
4.Proper authorization object has to set in the authorization
profile of the users to strictly use this Change number.
Reward points and close this thread.
5.You have opened a thread in ERP forums under the same
topic.Please reward points also for that & close the thread.
Regards
Mangal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any can send me a detail screen shot flow to create a change number for material.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can create change no. using transaction
CC01.Then u need to select the object types like material,BOM,Routings and then assign the objects(like material) for which this change no. is valid.
Then,when ever u go to change transactions,system will ask for the change no.U have to mention this change no. n changes will be booked under this,which give u a track of changes done.However,for more details refer the link below:
http://help.sap.com/saphelp_46c/helpdata/en/d4/09c0cfa3a811d189be0000e829fbbd/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.