Hi Experts,

I wanted to know the steps and best practices for implementing and configuring PP module in FMCG industry. I was thinking between PP-PI (process) and Discrete production as I've seen both running in FMCG industries, another option is Repetitive Manufacturing, so which one would be more preferable and their pros and cons. Also I'm thinking of Batch management so kindly let me know in regards of that. I've seen many posts regarding PP configuration but never for FMCG specific. It is a Biscuit manufacturing company, produces 6 different kinds of biscuits, only flavor is different, all processes are identical.

BR,

Shankar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Oct 16, 2016 at 02:23 PM

    Hello,

    Check the below link for basic difference between discrete and repetitive manufacturing,

    https://wiki.scn.sap.com/wiki/display/ERPLO/Discrete+Manufacturing+Vs+Repetitive+Manufacturing

    The FMCG process of biscuit manufacturing would fall under process manfacturing industry.

    Batch managemenet is integrated with process orders, so I would suggest you go for process order implementation.

    I am not sure how well repetitive manfacturing is integrated with batch managemenet.

    Best Regards,
    Ameya Beri

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 16, 2016 at 01:58 PM

    Hi Shankar,

    When you are only dealing with manufacturing of 6 different kinds of biscuits, I would choose at first to investigate repetitive manufacturing with batch traceability. This is the least complicated solution.

    Second best option would be PP-PI with the justification that it was designed for the process industry.

    Regards, John

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 17, 2016 at 11:41 AM

    Hello Sankar,

    As you only saying that 6 different types of biscuits they are processing hence it would be a PP-PI Situation..

    here you have to consider how many Co-Product and By-Products you will be receiving after the production, if only one FG if you receive then better to go ahead with Discrete manufacturing

    Regards,

    Venkatesh

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 19, 2016 at 05:06 AM

    Hi Shankar,

    In buscuits ind you need to use batch managment. apart from this, check how long the order is running on shop floor, if the order is running for longer period of time than you can use REM.

    Since it is a simple process, you can use REM or discrete both but you need to discuss with CO person.

    regards,