Release Strategy

Hello all ,

Exact problem is,

The PO has been approved all the way through all 5 levels. The original cost of the PO is $100,000.

Now , The PO price in the Net Price field was then lowered to $65,000.After the price was lowered, it canceled all of the approvals and retriggered the approval process. If the Net Price is raised, then the approval process should be retriggered, and it is; however, it should not be retriggered if the Net Price is lowered.

The same thing happens when the quantity is changed to lower the price. The original PO has been approved all the way through for 100,000 pcs at $1 for a total of $100,000.

When the quantity is changed to a lower number to bring the price down to another approval level, the approval process is started all over again

Thank you.

Sidds

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 21, 2007 at 12:46 PM

    Hi

    Go to release strategy for PO ( OMGS ) and in release indicator set changiability as "2" Changeable, no new determination of strategy

    which in turn will not trigger any new release strategy on changing PO amount or Qty

    Vishal...

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 21, 2007 at 12:51 PM

    Dear siddhesh,

    have you assigned the characterisics net order value

    FRG_EKKO_GNETW to your class in release strategy.

    if maintained,give the net order value equal to $1,00,000 in the classification in release strategy.

    dont mention any <= in this value.

    TRy out

    Regards,

    velu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 21, 2007 at 01:07 PM

    you do this settings in IMG.

    Material management >purchasing >PO >Release proc for PO >Define Release procedures for PO

    Here in this we will assign the values in classification part.

    Hope this will help you.

    Regards,

    velu

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.