Exception Message Selection Group

Former Member
0 Kudos

Hi all,

I'm trying to create exception messages with MRP/MPS run under selection group 5(Exception during BOM explosion) and 6 Exception during availability check. Can someone pls let me know of when such an exception/error message can be triggerd?

Thanks and Regards

Deepak Prasanna S

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear,

If you donot know when this EM should appear why are you changing it?

anyway...explanation is as below

5 and 6 triggers in the following condition

EMGroup -5

EM text-when this mesages apprearas

50 No BOM exists

52 No BOM selected

53 No BOM explosion due to missing config.

54 No valid run schedule header

55 Phantom assembly not exploded

EMGroup -6

25 Excess stock

26 Excess in individual segment

40 Coverage not provided by master plan

50 Shortage in the planning time fence

57 Disc. matl partly replaced by follow-up

58 Uncovered reqmt after effective-out date

59 Receipt after effective-out date

70 Max. release qty - quota exceeded

96 Stock fallen below safety stock level

I hope u understood....please come back if required

Edited by: Rajesha Vittal on Dec 21, 2007 8:11 PM

Former Member
0 Kudos

Hi Vittal,

We are basically doing some system testing for the client, which invloves a case where-in this exception message appears when MRP/MPS is run. Though i created a material without any BOM or Routing, when i ran the MRP, no Exception Message was created. Thats why I wanna know if any setting needs to be done in the material master for this exception messgae to be created!!!

Thanks and Regards,

Deepak Prasanna S

Former Member
0 Kudos

any replies to this....plsss..

Former Member
0 Kudos

Hi,

Please try with following points,.

Exception creation message for BOM selection.

1.Create a planned order start date is earlier than the BOM valid from date.

2.Change the BOM status at CS02

Regards

Pradeep