error in mfbf

Former Member
0 Kudos

Hi Gurus,

I am doing mfbf against plan order system giving me error

"Planned order (46) is only allowed for make-to-order production"

My strategy of material is "81"

From witch t-code I have to go for back flush.

please suggest me

Nilesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member189817
Active Contributor
0 Kudos

Hi Nilesh,

Do backflush in MTO tab in MFBF.You might be entered in MTS.

Answers (1)

Answers (1)

former_member196398
Active Contributor
0 Kudos

Nilesh,

Are you using REM? Is the material Defined for REM? If yes, then

I think the planned order was manually created and it was not created from Sales order.

Regards,

Prasobh

Former Member
0 Kudos

Mr. prashob,

We are using REM and created pl. order through sales order

but I can't do backflush through mfbf.

Nilesh

former_member196398
Active Contributor
0 Kudos

Nilesh,

I think then you might have used the Make-to-stock tab in MFBF to input the planned order number. Use the Make-to-order to input your planned order.

Regards,

Prasobh

Former Member
0 Kudos

Hi,

I hope u have already maintained all settings for Rem flow.

Have u tried with “Make order” tab for back flushing at MFBF.

Plz let us know the Error message Number.

Regards

Pradeep