BPM Control step issue

All,

We have had a BPM scenario that was working in the XI3.0 and we exported and imported the same into another environment PI7.0

In the new environment - there is a control step that raises time out after 2 minutes, that doesnt seem to happen. The infinite loop goes on for ever and we have to delete the workflow manually.

The BPM is very similar to the standard collect pattern based on time.

Any ideas?

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 20, 2007 at 10:13 PM

    Hi RK,

    I think you need a special background job running to handle the dedlines. Please check with the XI Basis guys to see if this job is running or not.

    To my knowledge, the program RSWWDHEX should be scheduled in a job for any of the BPM deadline to trigger.

    Hope this helps,

    Sumant.