on 12-20-2007 11:15 AM
Dear All,
I need ur guidance ,,,while creating task list we maintain planner group & maintenance work center, now i think we should attach this task list to equipment with the same PG & MWC....
But like we can have motors at different Mainetnance Work Centers n Planner group, so we have to create same task list in different work center & planner group????????
Plz guide
rgrds
DM
Dear Deepak
Sry. U do the small change as mentioned by thiyagu then ur probs will be solved.
Thenna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Deepak
The task list can create with out planner grp, mtc work center.
See as u aware we are going to utilise the task list at maint plan only. here while creating the mtc item u should enter the Tech objs like Equip or FL.
Then ur mtc item automatically takes the planr grp, wrk center accordingly. The orders will also create same as equip has.
If we are creating the mtc order with out schdule directly by task list selection here also same logic will apply as mentioned earlier . There is no confusion. I think i given some sparks to u.
Thenna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi deepak
whatever work center and control key speciifed in the task list will be copied to the order ,if you maintain main work center and planner group in task list header different from the maintenance plan ,then maintenace order will get generated based on main workcenter and planner group speicified in maintenance plan ,whereas the performing workcenter and control key will be copied in to the order from task list
regards
thyagarajan
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.