on 12-20-2007 7:18 AM
Hi
Can anyone plz let me know the meaning and relation of above terms.
I tried to know from sap help but not able to understand much.
Thnx
Nilesh
Hi Neel,
As explained above you must have understood about these terms.
I'll continue the example taken by SVP in explaining Phantom assembly in more deatil.
First of all we sholud be clear that engine needs to be an assembly because it consist of a large no of parts and you cannot include these directly in the BOM of the car .You need to logically assemble all these parts and that logical assembly needs to be called as engine.Secondly why do we want to make it Phantom? This is because as soon as engine is made or assembled it is fitted into the car and as such it does not exist alone because we being a car manufacturer we don't sell engines nor do we keep an inventory of the engines.
Hope this will make Phantom assembly more clear to you.
Rewards if found useful!!
Anshul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Neel,
Assembly is nothing but product which made of independent components
For ex CPU
CPU is the final product
Hard disk
Processor,chips etc are the components that go into make a CPU
BOM
NOthing but details of components/ sub-assemblies /assemblies that go in for making a final product
Ex-Computer-Final prodcut
Assembly->Monitor,CPU
Sub assembly->MOther board unit
Components -IC chips ,wires etc
Pegged requirement
Is nothing but dependent requirement
For making one computer i need one CPU,1 Monitor
CPU & Monitor are dependent reqmnt
This term is used in various places ,EVen in APO its used in SNP
Phantom Material
Let me explain this with Ex
Car is the final product
In that you have lot many things going into make a car
consider Engine as one part
For making that Engine you need various components
Now engine can be declared as phanotm material
By doing so what will happen is all the rqmnts (after MRP) will be created for the components to make the engine & no reqmnt will be genarated for engine
Hope the above explanations are clear
Reward points if useful
Revert back if you have futher queries
Regards,
SVP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Assembly - whenever any finished component gets mnufactured then with assembly of those semifinish material you will get one end product called as Assembly.
BOM - your product requires semi- finish and raw material then that should get summarized in one tree structure i.e. you will start to build BOM right from semifinish and then finish material.
Pegged requirement - Independent requirement are for final end product and dependent requirent or pegged requirement are for child items
Phantom material- its a imaginary material for to manufacture this it requires child items but as a whole assembly its a hypothetical one.
reward points if you find it useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.