Dec 20, 2007 at 03:40 AM

How to transfer stock material from unrestr. stock to project stock?

355 Views

Hi all:

Material is procured directly to stock, unrestricted status. But later on, such material are assgined to be used within a project, a production order deployed (t-code: CO10).

I want to issue the material to the production order, but SAP issues a message telling that only material with special stock status Q can be issued.

My idea is to transfer the unrestricted stock to project stock. But I can not find any standard Movement Type in SAP to handle this transaction.

Is there such Movement Type? Or do I have to create a new one?

Regards.

Andy