Hi ,

Can any one of you please advice me where i can find the relation between a Operation and Phase used in the master recipe.

I mean , is there any database table where i could find the link between an Operation and Phase in Master Recipe

Thanking you

Regards

Raj Kiran

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Raj Kiran,

In PLPO table if field value is "X" for PHFLG, then that operation is phase check the value of field "PVZKN" for that record, and pass this value in PLPO table for field "PLNKN" to get the VORNR (operation assigned to).

Regards,

Prasobh

Former Member
0 Kudos

Hi Prasobh,

Thank you...my issue is resolved.

Regards

Raj

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Combine tables PLKO and PLPO in a query to acheive that..