Hello Geeks , guys I´m trying to execute t-code md04 with indidual access and a specific material for a specific plant, but I get the following error: the date 2168 is not convertible (Please correct). why is that ?.
Ali,
probable reason could be that some of the requirements for material/plant may be falling out of the validity period of the factory calendar. Please extend your factory calendar assigned to the plant for couple more years.