Hi,

How to create and maintain a BOM with mulitple revision level.

Thanks in Advance

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member184655
Active Contributor
0 Kudos

Dear Madhan,

Do you mean to say you want alternative BOM's or else

simple BOM,that's at one moment or one fixed point it should

be having only one BOM ,with a revision level?

See for deleting or modiying the BOM with revision level you

need to use ECN - Engineering Change number.

So whenever you are using an ECN for modifying the

BOM,enter the revision level - in the field reason for change

while creating the Change number in CC01 or using change -

CC02.

So this is one way of handling this issue.

Please check & revert back if anymore help is needed.

Regards

Mangal

former_member184655
Active Contributor
0 Kudos

Dear Madhan,

I have sent you some screen shots regarding Change Number

creation for Material & BOM.

Please check & confirm.

Also dont forget to close this thread.

Regards