User Exit for releasing assigned PM orders to Network Activity

Former Member
0 Kudos

Hi All,

Our business scenario calls for releasing assigned PM orders once the system status of Network Activity to which PM Order/s are assigned , is released. We are working in SAP 4.6 C

Request your help if there is any user exit for CN22 which can be of any use to achieve this or any other way for achieving the same.

Thanks in advance

with regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Abhijit,

How are you adding the PM orders to PS activities manually or using PMPS ref.?

Regards,

Pavalavel

Former Member
0 Kudos

I am attaching it manually

Former Member
0 Kudos

Try with these user exits...

PPCO0018 -Check for changes to production order header

PPCO0019 -Checks for changes to order operations

PPCO0007 -Exit when saving production order

Check when these exits trigger. We use a different procedure in our case of IS A&D where we have standard functionality for this using PMPS reference, which is not available in normal R/3.

Regards,

Pavalavel.

former_member201206
Active Contributor
0 Kudos

Hi ABHIJIT SEN,

I am afraid, there is no such exits, as the PM orders are not locked at all during you process the network like CN22. Without lock, a object can not be changed at all. Just check the SM12, if such pre-condition is filled or not.

Kind regards,

Zhenbo