Hi All,

I am facing an issued while changing the Budget profile.

Previously , configuration in OPS9 was Activation type 1 and only overall is ticked.

Now in OPS9 configuration , Activation type is 1, both overall and released are ticked, i have created a project and allocate budget in cj30 and release the same in cj32, however still WBS status is only BUDG , it should be, BUDG and AVAC.

I run CJBN and all the previous project status changed to AVAC, however while creating new project i am facing same issue .

In CJ32 , in availability control info: Availibility control is Inactive is coming

Any clue for system behavior

Regards

RAJIV

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi Rajiv,

I remember we need to check either Overall or Release, else how the system will determine when it has to update the AVAC ?

Why you changed the configuration by checking both ?

There are certain number of blogs available on Budget Control, kindly refer it.

Regards

Terence