Former Member
Dec 17, 2007 at 03:53 PM

KKA2 & Shortened fiscal year

22 Views

Hi

We have jsut shortened our fiscal year, so it ends on 31.12 instead of 31.03. However we have billing milestones for 01.01-31.03, and the Planned revenue was entered for the current year only. This has resulted when running RA via KKA2 that any planned revenue for Jan-March is excluded. A temporary fix is to change the billing milestones to April, but we have thousands of projects. Has anyone else encountered this issue? We are on 4.7