Dear

I dont think as a std SAP transactions will allow my below req.

1. I have created task list mtc stratagy as XXX. but i need to change as YYY.

2. The same mentioned above for MTc plan

3. I would like call the Mtc order on key date

Example Pump has weekly, monthly tasks.

1. Weekly schdules i need for every month 1st, 8th, 15th,22th no need 29th .

2. We can call the monthly ops thro Key date . Here if i have mentioned in stratagy as 28 days instead of 30 days it will call?

Pls any one have the soln

Thanks

Thenna

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear

Thnaks. But i cant delete the task list Ops Since N no of task list need staratagy change which is assigned to mtc plan.

Ok i dont think its possible

Former Member
0 Kudos

Dear

Any help pls

former_member187991
Active Contributor
0 Kudos

hi

i think it is not possible to change the maintenance strategy once assinged to task list,other option just try in the task list select the operation and select the maintenace package ,here delesect all the maintenance package alloted and then try to change it

regards

thyagarajan

former_member187991
Active Contributor
0 Kudos

hi thenna

first delete all the operations in the task list ,then system wil allow you to change the maintenance strategy

i dont think it is impossible to change the maintenance strategy in maintenance plan

regards

thyagarajan

Former Member
0 Kudos

Dear

Pls tell me is it possible to change the exist mtc startagy for task list, mtc plan