I am procure about a dozen different materials for which all require the same capacity for transportation. I may have different material mixes on different days. I would like for the sum of calculated requirements to total a certain number of units thus allowing me to utilize my transportation resources more effectively.

Is it possible to create an order multiple or rounding value for a family of combined parts? I would like the sum their daily requirements to total a multiple of a fixed value.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
Nov 04, 2017 at 01:12 AM

I have not yet seen that MRP takes care about transportation capacity planning.

It creates requirements (planned orders / requisitions) which may end in purchase orders.

Capacity utilization for transportation can be done from Logistics Execution reports: