Hi experts,

we use the unloading point in the work order header as an information field for manufacturing.

Now I see one plant has history requirement on this field unloading point/ WIP location. So we see when & by whom the information was put in there. Where can this be turned on for other plants?

Thanks & regards,

Anne Mielke

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Caetano Almeida
Oct 25, 2017 at 05:13 PM
0

Hello

There is no standard feature to enable history requirements for production orders.

The following note provides a solution using an user-exit, which you can adapt to check this specific field:

390635 - Change documents for production and process order

Regards,

Caetano