Hello,

We have executed CDA both from planner and Ad-hoc as well. After completion of the assessment (with review completed), the result is not getting updated in the control.

Result is being displayed as empty. The rating was set as Adequate while approvibg assessment.

GRC 10.1 SP16.

Kind regards,

Yashasvi

Accepted Solutions (1)

Accepted Solutions (1)

rajeshwari_akkamgari
Active Participant
0 Kudos

Hello Yashasvi,

Do you still face this problem? If yes, check SAP note 2426474 - Assessment Result is not Displayed When Customizing is Missing

Thanks

Rajeshwari

former_member226273
Active Participant
0 Kudos

Hello Rajeshwari,

We created OSS incident and one of the same NOTE has been suggested by SAP,thus resolved the issue.

Kind regards,

Yashasvi