Latest and finish start dates.

Former Member
0 Kudos

Dear all,

1.What is actually meant by latest and finish start dates?

2.In my maintenance order, when i am using my workcenter against each operations, the earliest start date, earliest end date, earliest start time, and its finish time is calculating based on the WORK not on DURATION. How it normally take ?

3.Even if we are using indian calendar in the workcenter (Also capacity uitilization is 100%) system is not calculating the actual time (Scheduled done manually also by click the scedule icon in the order screen.)

Regards,

Prasanna.

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi prasanna

latest and finish start date is based on the notification which is assigned to the order, in IMG for notification priorities you would specify the sch,start & finish days for each priority which will calculated the start and finish dates

in maintenance order the sch,start and finsih date will be calcualted based on the duration only ( which has calcualted based on work and number of employees).in your case in capacity master data you have specified 100% and start and finish times as 08.00 and 17.00, length of break 1.00 hr,then in the maintenance order if you specify your work and number as 1, the duration will be calculated as 1 and the dates will be calculated as

stard date & time 14/12/07, 08:00

End date & time 14/12/07, 09:07

sytem has calculated the times ( total working time-operating time)/Operating time for each HR, in this case 9-8/8 which is 0.125 hr or 7.5 minutes

regards

thyagarajan