Independets Requirements Consumption

Dear Gurus,

I want to set up the following process:

Im create the planned of independets requirements in PIR(MD61) for plant "0001", but my production whas ser in different

I can in such a way produce a material in plant "0001" how much in plant "0002".

However, the planned of independets requirements (MD61) they are only created in plant "0001".

The sales order are created in such a way in the plant "0001" how much in the "0002"

the question:

Is possible that the sales order of plant "0002" should consume the PIR in plant "0001"

regards,

Flávio Molina

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 27, 2007 at 06:36 AM

    hi falvio,

    this can be achieved if u define a special procurement key 80 whic is production in alternate plantwith procurement type e" inhouse production"

    make sure you configure it to the plant before executing.

    in this u plan for plant 1000 and produce in plant 2000 which reduces PIR of of plant1000. i think u should give strategy 40 for this.

    regards

    sanjeev

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 13, 2007 at 11:42 AM

    Hi

    PIR's & sales order are both requirements.

    sales orders of one plant can not consume the PIR's of other plant .

    It is not std SAP.

    Regards

    YMREDDY

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 26, 2007 at 06:12 PM

    You can consume PIR's from other plant if you are using strategy 63/60. You would have to enter the planning material number and planning plant (0001) in the MRP 3 view of the material master of the material at plant 0002.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 27, 2007 at 04:38 AM

    Both PIR and sales order are requirements. Anyhow if you want to plan the material in other plant 0002 apart from plant 0001, you have to adopt planning strategy 63 and you have to determine planning plant in MRP3 view in material master.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.