12-12-2007 10:20 AM
Hi guys,
i'm currently working on a Cost of Production report. In this report the client wnats to have the total quantity produced for a particular period, the planned (raw material cost and the packing material cost), the actual (raw material cost and the packing material cost) and the variance report.
I am being able to get the planned RM and PM cost but i have no clue from where i should pick the actual RM and PM cost.
Please help me out reagrding this. It quite urgent.
Points will be awarded generously for useful answers.
12-12-2007 11:07 AM
hi,
Check the Table for budget costs BPEJ for the costs related to WBS elements
check the fun module K_CO_OBJECT_BALANCE_GET
also you have to calculate the costs of the network orders
also you can check the COSP and COEP tables
wrttp field is the differentiator between actual costs and estimated costs
01 means estimated cost
04 means actual costs
************************************
or you can check CKM3 transaction by providing material and period .you can view price difference if any.
Reward for helpful answers
Thanks
Sivaparvathi