Routings operations aktivity type

Former Member
0 Kudos

Hi all,

I created costing tab of work center after routings created. Then after routings , we created costing tab of work center. But now I don't see activity type in routings operations. What can I do? How can I solved this case?

Thank you and best regards,

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Hilal,

Follow this sequence.

1.Activity types creation for Cost centres(KL01) and cost center's creation using KS01,assigning rates for the activity

types Costcentre wise(KP26).

2.Create work centres(CR01) and assign the proper cost centre in the cost centre

tab and the activity type where in the activity type must have got some rates for

that cost centre.

3.Creating Routings/Rate routing(CA01/CA21) for the materials and assign a work

centre where the operation is to be performed.so for the activity's to be done in

that work centre,maintain the time for each activity type.

Check this & revert back if any more queries.

Regards

Mangal

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Create workcenter & fill up the activity type.

After that create routing.

Regards,

Dharma

Former Member
0 Kudos

Hilal Çakir ,

In the routing remove the respective line item or the work center,save & come out

Go back to the routing & insert new line item/fill the work center

Now check you will see the activity field updated

Revert back if u have further queries

Reward points if useful

Regards,