on 12-12-2007 5:50 AM
Hi
We don't want the user to change the price in the PO .Once the Purchase Requisition is released , we want to allow for lower limit , but not for higher limit.How to do it in the PO for released Purchase Requisition.
What are the settings needed to activate in the release strategy Thanks in Advance
Nick
Thanks
How to accept the less value ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
While creating PO with ref. to PR Price field is not copied from PR.It is copied from Inforecord/contract etc.
PR price has no control over PO price.For this u have to set Release indicator in PO Release strategy ( If u set changiability as 1 - U can not change Po after Release ) Which in turn will restrict PO price change after PO release
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I want to accept the less price or not converting the full qty in to PO.but not the above value approved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes u can do it
Release indicator i think 4 if you marked you can no change doc after relase
\
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.