Hi PP Gurus,

Is there any Standard Information Report which will give me Workcentrewise Planned / Actual Activity (based on Activity Confirmation) Analysis Costwise for month, half year, Yearly based?

Thanks in Advance.

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Pradeep,

Check with these reports.

S_ALR_87011775

S_ALR_87011776

S_ALR_87011777.

Regards

Mangal

Answers (4)

Answers (4)

Former Member
0 Kudos

Pradeep,

Rvert back if you have further queries,else reward points n close the thread

Former Member
0 Kudos

Hi,

Please try with std report MCPQ

Regards

Pradeep

Former Member
0 Kudos

Try Using the Capacity load reports like CM01, CM02.............

Hope this helps you find some information.

Former Member
0 Kudos

Pradeep

Try in COOIS under List confirmation & give the work center details under sub header -Select At operation Level

Inside the repot you can add/remove the fields in change lay out

Reward points if useful

Regards,

SVP