Is there any user exit or BadI that gets triggered when the quantity is changed in the servive tab of item detail in purchase order.

thnx

Priya

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

u can rectrict change by authorisation, track by version management, not allow to change by rel. strategy.

Former Member
0 Kudos

Hi Santhosh,

Thnk u for ur immediate response.

But I have to check a condition that the quantity must not exceed the quantity of purch req.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If u do not want PR qty to exceed in PO i.e. if PR is of 100 then PO should be of 100 and not more than this

then you have to make message 06 076 as error message in

SPRO>MM>Purchasing-->Environment-systemmessages.

Vishal...

Former Member
0 Kudos

Hi Vishal,

U r right . But i my item category is 'D' 'service'.

So quantity is always 1 in item overview.

I want to validate with the quantity in service level.

Former Member
0 Kudos

Check the value change allowed bet PR and PO