on 10-17-2017 4:32 PM
Greetings All ...
Following a Solution Manager 7.2 upgrade, I am trying to use the Normal Change Transaction Type with a Continual Cycle. But the option to select Normal Change in the Scope Assignment Block is not available.
The Normal Change is selectable with Phase Cycles. But the Phase Cycle documentation suggests it is for Implementation and Upgrade Projects. My goal is to use the Normal Change with the Continual Cycle for Maintenance.
Am I going about this the wrong way, or have I neglected a segment of Transaction Type configuration in my Post Upgrades efforts?
Sincerely ...
Stephen McDowell
Hi Stephen! You can use NC in SMAI starting from SM 7.2 SP6
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Per the available documentation, the Continual Cycle (SMAI) is meant for Urgent Changes only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.