on 12-10-2007 11:50 AM
Dear Friend's
I have created project upto level 2 wbs element.with ext services.
In Budgeting,
In CJ30 Tcode i have allocated budget Rs.100000/-
In CJ32 Tcode i have released above mentioned same amount for WBS 1.
In Purchase Ordering,
While creating PO In ME21N Tcode i have taken services for WBS 1 for which PO net amount is more than Rs.100000/-
When i go for saving of PO.The system must show Error "PO Amount is more than Released Budget.
Pls tell me the customizing setting for above mentioned scenario.By doing this setting system must show error while saving PO.
Pls help me urgently.
Thanks & Regards,
Sandeep N.Theurkar
Hi,
1. In your budget profile, tick the release indicator
2. In SPRO>PS>Cost>Budget>Define tolerance limits
3. Run CJBN ie Reconstruct Availability control for your project.
Reward points if useful
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Martina,
I have checked all the settings, everything is correct.
Also AVAC gets active when i do CJ30 & CJ32..but it is not giving error in ME21n
Please provide your email-ID so that i can send the Report screenshot to you.
Thanks & Regards
Sandeep
Message was edited by:
Sandeep Theurkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sandeep,
Please check for excempt cost elements in the budgeting customizing. This might explain why availability control is ingnoring your PO.
Hope this helps
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sandeep,
As far as I see, all the customizing settings are correct in this case. But just to summarize, please make sure:
a) In budgeting profile (OPS9) make sure flag "releases" is set
b) In CJ32 verify you have released budget for the WBS element (or superior)
c) In CJ02 verify that status BUDG and AVAC are active for the WBS element
d) In customizing path Project System > Costs > Budget > Define Tolerance Limits make sure you have entered the necessary tolerance limits for your budgeting profile. At least, one entry with Activity group ++, action 3 and usage 100,00 is necessary in your case.
e) In OPTK transaction, please make sure you have not included any cost element for your controlling area.
f) In ME22N make sure the PO is correctly account assigned to the WBS element
Once all this is done, please run CJBN and retest.
If you still don´t get the error when posting the PO, please send the output of BPFCTRA0 report
Hope this helps
Regards
Martina
Dear Martina,
I have attached screenshot of Report in the following link,
http://www.4shared.com/dir/4932302/cebc3276/sharing.html
Please provide me solution.
Thanks,
Sandeep
Sandeep,
Thanks for the attachment.
In the report output what I could see is that, apparently, the availability
control has not been activated for WBS element XXB070001001 (or XXB070001000).
If Availability Control is correctly activated, you should be able to see the
distributable value and the assigned value next to the WBS element code. In your case, this is empty.
Can you please run CJBV and retest?
Thanks
Martina
Hi Sandeep,
You indicate the budget is Rs 100,000, and if the PO is for more than Rs 100,000, you want an error message to generate from the availability control check.
IMG > Project System > Costs > Budget > Define Tolerance limits.
Create a new record for your controlling area and budget profile. Select transaction group = ++, Activity = 3, and Usage = 101.
As noted by previous reply, ensure your budget profile is configured for availability check by release budget.
Regards,
Kent Bettisworth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.