on 12-10-2007 2:43 AM
Dear All,
Plz advice, is there any user exit for CJ20n(project builder) in order to check available budget when we create reservation under a network/activity for a project?
Many thanks in advance.
Hi,
Budget functionality is available against actual / commitment items, but n't against reservation of materials as there cane be reservation at projects or plant level. Morever there is no such user exit in CJ20N.
If you can make developments of reservation agsinst network as committments items then budget functionality may work in that case.
Hope this will help you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I doubt if you can make the system treat Reservations as Commitments and check against budgets.
But in case of PR or PO, Budget is anyways checked if availability control is active in CJ20n provided in the tolerance node (under budget node SPRO) PR/PO is mentioned in tolerance group.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.