Hello,

If all the inspection characteristics are same for goods receipt inspection,recurring inspection,stock transfer inspection,manual inspection etc. , can we assign same "Task List Usage" to all inspection types in customizing ? By assigning same Usage e.g. Universal , I can avoid creation of multiple inspection plans for different usage.

Thank you in advance

Regards

Sarang

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 23, 2017 at 07:52 PM

    Yes. The task list usage is assigned to the inspection type in configuration.

    You can then have one plan for all inspection types. Be careful of doing this however and make sure you take into account all FUTURE unknown requirements.

    Once lots of data is in the system it can be difficult to make changes.

    If you have a small company and simple types of products, it might be fine to do this. But as you get multiple sites, acquire new plants or businesses, expand product lines, etc. etc. you might find yourself needing to make changes in the future thus requiring some extensive master data changes.