Move hardware during DMO run

Oct 18, 2017 at 11:56 AM


avatar image

Hello Boris,

We´re doing an upgrade and migration to HANA DB with SUM for DMO.

In order to increase the performance and reduce downtime, we´ll move SAP (PAS where DMO is running & source DB) to a most powerful hardware. The move is estimated to be done while SUM DMO already started. At the time of the move, DMO will be stopped asking for some input and then the move will be done. After the move, the input will be given and then proceed. Do you see any issues with this or there are something that we must be aware when we´re moving to another HW while DMO is running.



10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Boris Rubarth
Oct 25, 2017 at 02:26 PM

Hi Jim,

moving the hardware during SUM/DMO is not recommended, as the tool is aware of the host name.

Did you consider the approach "DMO with System Move" already?