Hi
It purely depends on The size of Client and Its Business process and The SAP Solution (e.g. SAP B1, MySAP SAP ECC etc)
Refer below link on sdn
Typical Duration
Project preparation- 2 Months
Blue print - 3 months
Realization- 4 months
Fina preparation- 2 months
Golive
There is Hard & Fast rule that all project go exactly,This depends up on clients also and they should provide the information and depends up on them also
Message was edited by:
SHESAGIRI.G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
it all depends on the project requirements and all other factors normally it will from 6 months to 1 year or a bit more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.