Hello,

I want to look at all the PM plans I have scheduled to break in the next 12 months

From there I would like to see all groups and operation short texts, operation work centers that are attached to the PM plans

What transaction would I use to view this without actually breaking the plans through IP30?

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Oct 18, 2017 at 11:21 AM

    Jack,

    IP19 is the most suitable transaction..

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 19, 2017 at 04:42 AM

    Thank you. This is what I was after. Appreciate it!!