For the EWM QM Follow-up Action - Reject UD to stock type Blocked?

In configuration we have the option to do Putaway or Scrap in EWM as a result of a QM Usage Decision. Within the Scrap configuration, the stock type is identified as BB and per system design, the stock type is updated to S# (Scrap) based on the a Scrap/Reject UD. How can we update this to be a B# (Blocked)?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 22, 2017 at 04:34 AM

    Hi Fay,

    As per the system design ,Follow up action code ( QM Usage Decision ) has a parameter internal follow up action code scrapping .This scrapping is related to stock type role as scrap .

    Flow: Decision Code( QM Usage Decision )->Follow up Action code-> internal follow up action code

    In Configuration of EWM, If you want only block ( not scrap ), then you can change internal follow up action code as Putaway for delivery and NST as BB in below Configuration

    EWM->IMG->SCM Extended Warehouse Management->Cross-Process Settings->Quality Management->Result->Decision Code/Maintain Follow-Up Action

    Flow: Decision Code( QM Usage Decision )->Follow up Action code-> internal follow up action code

    Please check and let us know if you have further queries.