Change Destination Bin when confirming a TO for Posting change

lars_axelsson
Explorer
0 Kudos

I would like to be able to change the Destination Bin when confirming a TO for a Posting Change. The background is that we are using QM and when posting a quality lot from Q-stock to Available I have configured the WM Movement Type (321) to not make the posting into the same Bin. The TO is instead configured to generate a placement into the final Destination Bin.

The problem is that it’s not possible to change the Destination Bin when confirming the TO (trans LT12 & LT11), when the TO is based on a Posting Change.

How come that this isn’t possible when it’s a standard feature for regular TOs for placement, eg. MT 101? Is there a way to enable it or do a simple workaround?

/Lars

Accepted Solutions (0)

Answers (1)

Answers (1)

shailesh_mishra5
Product and Topic Expert
Product and Topic Expert
0 Kudos

hello Lars,

Even if you have configured destination bin change for the required storage type, under certain circumstances you cannot change the destination storage bin and confirming Transfer order against posting change notice is one of them

Yo can check the below KBA which encapsulates all the points

443916 - Dest. storage bin cannot always be changed during conf.

Best regards

Shailesh Mishra

lars_axelsson
Explorer
0 Kudos

Thanks Shailesh,

Yes, I know that it's a problem and how the standard configuration shall be done. What I'm asking for is a way to enable change of destination bin when confirming a TO for Posting Changes or a good workaround.

Best regards,

Lars

shailesh_mishra5
Product and Topic Expert
Product and Topic Expert
0 Kudos

I will test tomorrow and let you know whether some better workaround or any other alternative is available or not.

I need to check whether changing below configuration works or not.

Activating storage bin input

TO confirmation

Best regards

Shailesh Mishra