PO FOR COST CENTRE

if we create Purchase for Cost centre that is as acc assignt as K , If we made the GRN, Is the stock comes under our storage location or else It is automatically consumed under the Cost centre . Please let me know clearly the overall aspect of the same.

The best answer will be reawarded accordingly.

Add a comment
10|10000 characters needed characters exceeded

Related questions

7 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 11:35 AM

    Thanks for alll your fast response,,,,

    But now one user has made the PO against the cost centre for a perticular Materail and the warehouse person made the GRN for the same , but in MMBE the stock is showing under our Sloc . Please let me know how to solve or go about the same.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Ganesh

      Please check the control data of your account assignment category.

      The data might be changed.

      Please note even with account assignment, you can monitor stocks provided if the control data of AAC is adequate. Example: AAC "Q" - Project stock.

      Please check whether the control data of K is changed and made identical to Q.

      warm regards

      sairam

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 11:17 AM

    Hi,

    It will be consumed to cost center after GR.

    thanks

    suresh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 11:24 AM

    K meance cost center

    so when u do gr valua and qty u issue it to that cost center

    so qty dont comes to storage loc

    reward if usefull

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 11:27 AM

    it willbe consumed by the cost center.

    regards,

    indranil

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 11:28 AM

    dear ganesh,

    when you are creating a P.O. with ref. to a cost centre, the material is directly cosumed at that cost centre specified in the P.O.

    you cannot take that material in stock as it is consumed at the time of GR itself.

    Njoy

    Ashish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 12:12 PM

    Materials purchase for cost centers are consumed at the time of GRN. you cannot take it to the inventory. But if you create the Purchase order for Sales order (E) or for Project (Q) it will be shown in MMBE under the special stocks.

    thanks !

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 01:13 PM

    hi ganesh,

    whenever u give a storage location in a PO,

    stock quantity is in that storage location,

    and the value of that quantity is in cost centre accounts,

    when you see the stock overview with MMBE the stock is at the storage location,

    cost centre is not a physical location,

    only values are maintained at itemcategories,

    regards

    lakshmi reddy

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.